Cell Phone Tower Application Pending
Bell Atlantic Mobile Systems LLC d/b/a Verizon has submitted a Site Plan Review Application to install a 130' cell phone tower at 24 Post Office Road. This webpage is provided to keep citizens informed of the status of the application and opportunities to participate in the process. All Planning Board proceedings are open to the public. Here is the history so far, and the tentative schedule:
May 13, 2026 - May 26, 2026 Emails between Becki Dikitanan and Town Officials
June 11, 2026 Letter from Michael Hamilton to Planning Board
June 23, 2026 Planning Board Special Meeting to review the Verizon cell phone tower pre-application materials and prepare for the expected Final Application submission, and to review the Site Plan Review process in general
June 25, 2026 Verizon Final Site Plan Application Addendum: Notice to Abutters
July 8, 2026 Planning Board Regular Meeting: Address conflicts of interest and set schedule for Verizon Site Plan Review process
July 16, 2026 Verizon Final Site Plan Application Addendum: Responses to Community Concerns
July 28, 2026: Planning Board Special Meeting at Old Town Hall:
August 6, 2026 Email from Verizon Counsel with Easement & Completeness Table
August 6, 2026 Emails between Abutter Rebeca Dikitanan & Planning Board Members
August 6, 2026 Submission by Abutter Michael Hamilton in response to 7/28/26 meeting
August 12, 2026 Email from Abutter Rebeca Dikitanan re Completeness of Application
August 13, 2026 Email from Verizon to Planning Board with Civil Engineer responses to questions
August 13, 2026 Email from Abutter R. Dikitanan to Verizon Representatives re: Alternate Site
August 16, 2026 Email from Abutter Michael Hamilton re: Nobleboro Lawsuit
August 18, 2026:
August 19, 2026 - August 21, 2026 Emails between Planning Board Chair and Verizon Counsel
August 27, 2026 Email from Verizon Counsel re: Items Requested
September 1, 2026: Special Planning Board Meeting to review Verizon application
September 5-6, 2026 Emails between Select Board Chair and Planning Board Chair
September 9, 2026 Emails between CEO, Planning Board, & Abutters re: Lot Size
September 10-13, 2026: Emails between Planning Board Chair & Verizon Counsel
September 10-14, 2026: Emails between Planning Board Secretary & Planning Board Chair
September 11, 2026: Email from Planning Board Chair to Planning Board
September 11-15, 2026: Emails between Planning Board Member & Planning Board Chair
September 12-15, 2026: Emails between Planning Board Secretary & Planning Board Chair
September 12-15, 2026: Emails between Planning Board Chair & Planning Board
September 13, 2026: Email from Planning Board Chair to Parties with Draft Completeness Decision
September 13-15, 2026: Emails between Planning Board Members & Planning Board Chair
September 17, 2026 Verizon/Tarpon Towers Supplemental Application
October 1, 2026 Emails between Planning Board Chair, Verizon Attorney, and Abutter Becki Dikitanan
October 8-10, 2026 Emails between Verizon Attorney and Abutter Becki Dikitanan
October 11, 2026 Email from Abutters Bonni & Michael Hamilton